Sunward No. 85 Shield Launch Ceremony

Grand Commencement: The left-line shield of Nandan Section officially begins its journey.

6.28 m
Excavation Diameter

5,600 kN·m
Rated Torque Output

~550 t
Total Machine Weight

Taming the “Upper-Soft-Lower-Hard” Strata

The 838.74m Nandan Section presents a geological nightmare, featuring a mix of siltstone, mudstone, and mixed-face ground. Sunward’s engineering team optimized the cutterhead design to ensure stability when transitioning between soft soil and full-section hard rock.

Equipped with a 1,350kW power system, Sunward No. 85 is built for reliability in fracture zones with high groundwater pressure.

TBM Cutterhead Detail

Safety & Settlement Control

Smart Construction Monitoring

To protect existing schools, industrial parks, and high-voltage pipelines, Sunward No. 85 utilizes a real-time digital monitoring platform to maintain precise earth pressure balance, ensuring “zero-disturbance” in the urban core.

Leading Through Innovation

Sunward’s TBM solutions: Engineering reliability for the world’s most complex urban rail projects.

Explore Custom TBM Solutions

Sunward No. 85 EPB Shield Successfully Launches for Shenzhen Metro Line 17
This website uses cookies to improve your experience. By using this website you agree to our Data Protection Policy.
Read more